I do not want two jobs to run at the same time. These two jobs are in two different group and tables.
How can this be done in Control-M?
I do not want two jobs to run at the same time.
You could also make the jobs dependent on the same quantitative resource.
Create a quantitative resource with a max value of one and then in each of the jobs make them dependent on that resource being available.
Hint: In the Control-M/EM GUI select Tools --> Quantitative Resources --> New ... go from there.
Create a quantitative resource with a max value of one and then in each of the jobs make them dependent on that resource being available.
Hint: In the Control-M/EM GUI select Tools --> Quantitative Resources --> New ... go from there.
When the people fear their government, there is tyranny; when the government fears the people, there is liberty. - Thomas Jefferson
Resource Exclusive or Share
The name of the resource is the same in the two jobs's you has win upper and lower case,