Could someone have an idea how to schedulle a Job all Workdays except last workdat of year?
My scenario is, I have a regular calendar with all workdays of the year. Currently my solution is defining that the job should "active" all year unless the last workday of the year but this manually every year. I want to avoid not update that specific job every year becauseI will have to change de the active parameter for the next year.
Someone have another idea to achieve it without the active parameter
Im working with control-m 7
Thanks in advance
Aaron
How do I schedule all workday except last workday of year
Re: How do I schedule all workday except last workday of year
Hi
Here is a solution.
Using RuleBased Calendar
1 - Creating two RB calendar
1 ALL_WDAYS: including all working days
2 LAST_DAYOFY : including only the last working day of december
All of them could use regular calendar to know working days.
How to configure LAST_DAYOFY ?
In Day of Month type L1 using Regular Calendar or not.
Select WeekDays and AND operator
and seclect only december.
2 - In the Job Scheduling
Select RB Calendars :
ALL_WDAYS in RB Calendar List
and
LAST_DAYOFY in Excluded RB Calendar List
Here is a solution.
Using RuleBased Calendar
1 - Creating two RB calendar
1 ALL_WDAYS: including all working days
2 LAST_DAYOFY : including only the last working day of december
All of them could use regular calendar to know working days.
How to configure LAST_DAYOFY ?
In Day of Month type L1 using Regular Calendar or not.
Select WeekDays and AND operator
and seclect only december.
2 - In the Job Scheduling
Select RB Calendars :
ALL_WDAYS in RB Calendar List
and
LAST_DAYOFY in Excluded RB Calendar List
Re: How do I schedule all workday except last workday of year
Hello Fyot,
I don't see the exclude option.
I don't see the exclude option.
- Attachments
-
- jobOutput
- Captura.JPG (76.95 KiB) Viewed 30464 times
- jobOutput
- Captura.JPG (76.95 KiB) Viewed 30464 times
-
- Nouveau
- Posts: 3
- Joined: 18 Jan 2018 3:18
Re: How do I schedule all workday except last workday of year
Scheduling tab > Select schedule and then "Using Specific Rule-Based Calendars"aronfire wrote:Hello Fyot,
I don't see the exclude option.
In there it will give you two options:
Rule-Based Calendars List - Add your "All workdays" calendar in there.
Excluded Rule-Based Calendars List - Add your "Last workday of the year" Calendar in there.
Then just click on View Schedule and you'll see all work days are valid, except the last one.
Re: How do I schedule all workday except last workday of year
Hi Fyot,
But I dont have that option im working with version 7.
But I dont have that option im working with version 7.
Guilherme_HFA wrote:Scheduling tab > Select schedule and then "Using Specific Rule-Based Calendars"aronfire wrote:Hello Fyot,
I don't see the exclude option.
In there it will give you two options:
Rule-Based Calendars List - Add your "All workdays" calendar in there.
Excluded Rule-Based Calendars List - Add your "Last workday of the year" Calendar in there.
Then just click on View Schedule and you'll see all work days are valid, except the last one.
- Attachments
-
- tab_schedulling.JPG (77.19 KiB) Viewed 26608 times
- tab_schedulling.JPG (77.19 KiB) Viewed 26608 times
Re: How do I schedule all workday except last workday of year
Hi
Strange
RuleBased appeared with version 7
So verify your FixPack version
Strange
RuleBased appeared with version 7
So verify your FixPack version
Re: How do I schedule all workday except last workday of year
Thanks I will check that.fyot wrote:Hi
Strange
RuleBased appeared with version 7
So verify your FixPack version