I do not want two jobs to run at the same time.

Post by mlvats » 16 Jul 2008 3:23

I do not want two jobs to run at the same time. These two jobs are in two different group and tables.
How can this be done in Control-M?

User avatar
mauriziog
Nouveau
Nouveau
Posts: 807
Joined: 08 Jun 2007 12:00
Location: Varese - Italy
Contact:

Post by mauriziog » 16 Jul 2008 3:39

There many ways !

1) Have two different start time from two jobs
execution panel
submit between, to fields

User avatar
Lacoochee
Nouveau
Nouveau
Posts: 5
Joined: 25 Apr 2008 12:00
Location: San Antonio, FL

Post by Lacoochee » 16 Jul 2008 4:13

You could also make the jobs dependent on the same quantitative resource.

Create a quantitative resource with a max value of one and then in each of the jobs make them dependent on that resource being available.

Hint: In the Control-M/EM GUI select Tools --> Quantitative Resources --> New ... go from there.
When the people fear their government, there is tyranny; when the government fears the people, there is liberty. - Thomas Jefferson

User avatar
Walty
Nouveau
Nouveau
Posts: 473
Joined: 20 Jan 2006 12:00

Post by Walty » 16 Jul 2008 4:30

Why you don't use the Control Resources to serialise your jobs ?

Control Resources indicates the resources required by the job during execution and the type of control (shared or exclusive)

User avatar
mlvats
Nouveau
Nouveau
Posts: 7
Joined: 22 Apr 2008 12:00

Post by mlvats » 16 Jul 2008 11:00

Thanks.everyone for the reply. i used Control Resource Parameters - Exclusive and it did work.

User avatar
siipryasa
Nouveau
Nouveau
Posts: 11
Joined: 18 May 2008 12:00
Location: Mexico, D. F.

Resource Exclusive or Share

Post by siipryasa » 22 Jul 2008 1:44

The name of the resource is the same in the two jobs's you has win upper and lower case,

Best Regards