Page 1 of 1

how to know in control M taht job is sucessful

Posted: 05 May 2009 3:36
by dsu007
This might be trivial question But i am in a new organization where CONTROL M is being used to schedule the job and i am running 2 etl packages using the command line process of control m.
And then now the question is that my jobs2 is dependent on job 1.
That means job 2 will run only if job1 was successful otherwise agent should quit.
I have no idea how to achieve this, please guide me.

Thanks

ideas

Posted: 08 May 2009 12:03
by th_alejandro
Hello, follow this steps :
1) in job 1 define output condition, may be PART1-to-PART2, then
2) in job 2 define in condition, PART1-to-PART2

in this case, then agent only execute job 2 if job 1 finish OK.

hi

Posted: 08 May 2009 11:54
by malay
Just set condition and after successful completion you may check pre-requisite condition will be generate.