Page 1 of 1

To delay or HOLD the New Day Process

Posted: 27 Mar 2017 8:47
by Gopikkd
Is there any option to HOLD or delay the New Day process.

For Example, the New Day process would start execute @ 07:00 AM EDT. It should not start till 07:20 AM, and then should start

Re: To delay or HOLD the New Day Process

Posted: 22 Jul 2017 10:30
by fyot
Hi

It's not possible to delay NDP.
Anyway, using USERDAILY, you can delay to up to plan jobs holding job you will create to that USERDAILY scan.