(in/out conditions)

Everything about Control-M Server installation or setup.
Post Reply
User avatar
moha1984
Nouveau
Nouveau
Posts: 53
Joined: 08 Aug 2010 12:00

(in/out conditions)

Post by moha1984 » 22 Dec 2010 3:20

hi ,

please i am create two jobs with denpandance (in/out conditions) but the first job running more than two days and the second job was deleted by defulte after new date time if any body can help me for this issue please.



regards,
Moh

User avatar
catchtony
Nouveau
Nouveau
Posts: 50
Joined: 12 Sep 2008 12:00
Contact:

Post by catchtony » 22 Dec 2010 7:15

Put the maxwait under execution tab to 3 in both the jobs.

User avatar
moha1984
Nouveau
Nouveau
Posts: 53
Joined: 08 Aug 2010 12:00

Post by moha1984 » 26 Dec 2010 8:16

thank you a lot Mr. catchtony


what about resources the same conditions ?

Also , I am create two jobs with denpandance (resources) but the first job running more than two days and the second job was deleted by defulte after new date time if any body can help me for this issue please.