Job scheduling

Post by Gopikkd » 26 May 2016 11:15

Hi,

I have a job that should execute only on Last Sunday of each month.

How to schedule it..??

User avatar
fyot
Nouveau
Nouveau
Posts: 736
Joined: 26 Apr 2005 12:00
Location: PARIS
Contact:

Re: Job scheduling

Post by fyot » 26 May 2016 4:51

Hi

In the Month Days , add L1,L2,L3,L4,L5,L6,L7
and
In Week Days select Sunday

User avatar
Gopikkd
Nouveau
Nouveau
Posts: 154
Joined: 25 May 2009 12:00
Location: Bangalore

Re: Job scheduling

Post by Gopikkd » 27 May 2016 5:53

Thanks a lot. It works now..