Control Resource

All questions about Control-M jobs definitions
Post Reply
User avatar
Gopikkd
Nouveau
Nouveau
Posts: 154
Joined: 25 May 2009 12:00
Location: Bangalore

Control Resource

Post by Gopikkd » 04 Aug 2015 4:21

Control-M jobs are waiting for Control resource : ABC_CR_WLOAD.
No jobs are currently using this resource but still this resource is missing.

Could you please advice why it is showing like this? How to fix this issue..

User avatar
Gopikkd
Nouveau
Nouveau
Posts: 154
Joined: 25 May 2009 12:00
Location: Bangalore

Re: Control Resource

Post by Gopikkd » 11 Aug 2015 6:50

Anyone faced this kind of issue in your environment.

4 jobs are created with same Control resource with exclusive mode. When i check all the 4 jobs are waiting forCR... but no jobs are using that CR