Cyclic Job.

Post by pone2332 » 31 May 2013 10:29

Are cyclic jobs that run from the start of a previous run queued if the previous run is over the defined cyclic time?

I have a cyclic job which is scheduled to run every 15 minutes from the start of the previous run but sometimes the job runs for 20-30 min. I noticed the difference between some runs after a long run were short. Now, I know the run after 15min will occur immediately the current run is complete.

User avatar
Manii
Nouveau
Nouveau
Posts: 46
Joined: 28 Jul 2011 12:00

Post by Manii » 03 Jun 2013 8:49

hi pone2332,


answer is YES...

If you give rerun every 15 from job start time , it will calculate the time from job submission to finish .

if job run more than 15 min than next run should start immediately after the previous run ..

if you want to make gap of 15 min in each run then give all interval from job END

Regards,
Mani[/img][/url]