Schedule a job to run ALLDAYS except last business day

Post by Meanjean » 27 Jan 2013 10:53

Using Midrange Control-M 6.3, need to schedule a job to run ALLDAYS except the job should not run on the last business day of month. Is there a way to do this without a special calendar?

Thanks,
Jean

User avatar
ashwin080
Nouveau
Nouveau
Posts: 8
Joined: 12 May 2011 12:00

Schedule a job to run ALLDAYS except last business day

Post by ashwin080 » 28 Jan 2013 6:24

Yes you can schedule it. Using two calendars. One is which runs on all days and the other one is which runs only on business days.
You need to give the business days calendar under Months days and use -L1 in rules and select the OR option. Under weekdays mention All days calendar you will get what you need.

User avatar
Meanjean
Nouveau
Nouveau
Posts: 4
Joined: 24 Apr 2008 12:00

Post by Meanjean » 28 Jan 2013 7:54

ashwin080,

Thanks for the quick response!