Transfer jobs from a job group to a new scheduling group

Posted: 25 Nov 2009 5:26
by jennah_rekka
Hello there,

We have this problem in transferring jobs currentky in a job group and we want to moved them to a new scheduling group so that we can put some conditions in the group that allthe jobs in it will depend. When doing some revision in each job so it points to the new scheduling group, we cannot see the jobs moving there but then another job group is created but not a scheduling group. NOw when we write the jobs, all the transferred jobs have been lost. =(

Can you help me in this?

Thanks!
Jennah

Posted: 25 Nov 2009 6:12
by jennah_rekka
Hello,

I think the other term for scheduling group is schedulimg table or group scheduling table. It is more convenient to use this than the usual job group so that there is a group processing of jobs. Yet we cannot move the jobs from a job group to this scheduling group or table.

Regards,
Jennah

Posted: 25 Nov 2009 6:43
by ejtoedtli
I am not an expert on scheduling groups. Our company only uses a couple of them. Most jobs of our jobs are not in scheduling tables. However, I attended a scheduling class at BMC a couple of years ago and were told that jobs can not be moved into a scheduling group. The jobs have to be recreated as new within the scheduling table. This is what I had to do when setting up some awhile back. It was a bit of a pain.

Maybe there is an easy way to do it using exportdefjob and importdefjob.

Posted: 26 Nov 2009 12:30
by Mike_27_27
Have you 1. Created a new scheduled table. 2. Export exsisting table in question (via the exportdeftable cmd). 3. Do mass update to the exported defined table. 4. Define the table back to the newly created table. Cheers

Posted: 26 Nov 2009 12:36
by Mike_27_27
If you were not sure of command ... exportdeftable –u UserID –p Password –s EMGUI_P1 –arg C:\MIKE\TERMS\terms_sample_DDE_INT.txt –out C:\MIKE\XMLS\DDE_INT_20071220.xml