What's the MaxWait parameter ? How and why is it used ?

User avatar
philmalmaison
Nouveau
Nouveau
Posts: 1148
Joined: 08 Jun 2007 12:00
Location: Ile de France

Post by philmalmaison » 27 Jul 2009 12:35

it's how many odat the job will stay on AJF before being remove by the new day procedure
regards
philmalmaison

User avatar
malay
Nouveau
Nouveau
Posts: 9
Joined: 24 Jun 2007 12:00
Location: Bangalore

hi

Post by malay » 28 Jul 2009 6:18

I think Max wait will not be applicable for ON-Demand job [Pink color]...it will be not stay in control-M for next schedule.