Is it possible to have an alert if a job is last two times longer than usually (exectime X 2) but this job is not finished
I can't use Postproc because the job is allredy running
job too long
- philmalmaison
- Nouveau
- Posts: 1148
- Joined: 08 Jun 2007 12:00
- Location: Ile de France
you can develop a script scanning AJF, and shout when the job is > to a range calculated with averge duration.
I gave an example in http://www.scheduler-usage.com/Uploads/philmalmaison
have a look on it.
regards
Philmalmaison
I gave an example in http://www.scheduler-usage.com/Uploads/philmalmaison
have a look on it.
regards
Philmalmaison