Post proc with Latesub

Post Reply
User avatar
SCB_Karthik
Nouveau
Nouveau
Posts: 2
Joined: 25 Apr 2013 12:00

Post proc with Latesub

Post by SCB_Karthik » 25 Apr 2013 8:50

Dear all,

Control M generating false alerts on below situvation.

I Should get alerts on second day, but i am getting alert on same day.
In Postproc with Latesub, is allowing me to give upto 24:00hrs

Can any one help on this issue

User avatar
gglau
Nouveau
Nouveau
Posts: 317
Joined: 13 Jun 2007 12:00

Post by gglau » 07 May 2013 8:07

What do you mean by "same day" and "second day"?

Latesub is up to 24 hours from new day time of job ODate. If new day is 7am, Latesub can be up to 6:59 next calendar day.

If "day" means calendar day, Latesub can go to "second day" but before next new day time.

If "day" means ODate, Latesub has to be within "same day".

User avatar
SCB_Karthik
Nouveau
Nouveau
Posts: 2
Joined: 25 Apr 2013 12:00

Post by SCB_Karthik » 07 May 2013 8:50

For E.g Batch is getting ordered for date 8th mar at 6am HKT. and batch will start on 22HKT on same day. Some countries will start around 8am HKT on next day(9th may)and batch date is still 8th Mar. In this scnerio i am getting false alert.

User avatar
gglau
Nouveau
Nouveau
Posts: 317
Joined: 13 Jun 2007 12:00

Post by gglau » 08 May 2013 12:50

If 6am is new day time, job Latesub cannot be later than 6am next day. If you want Latesub in the next day, you have to derive something else to achieve the goal. There is no direct feature to support your requirement. The closest is to use BIM.

User avatar
Rocket
Nouveau
Nouveau
Posts: 11
Joined: 21 Mar 2013 12:00
Location: India

Time conversion may solve !

Post by Rocket » 20 May 2013 5:16

@ gglau
As you are saying " some countries" the time of NDP will vary, that is why ur getting this error. Better calculate time making a reference of "Server Time" (%%time).