Hi,
I have been seeing this for a past few days, that though the job executes successfully, the status of the job goes to red(NOT OK). Unsure why this could be happening.
Any help appreciated.
- Raven
Job completes successfully however not ok
- philmalmaison
- Nouveau
- Posts: 1148
- Joined: 08 Jun 2007 12:00
- Location: Ile de France
- samirniljikar
- Nouveau
- Posts: 2
- Joined: 17 Sep 2009 12:00
As mentioned in the earlier reply,please check if there is an Do ReRun statement in the Steps.Plus if there is an incorrect condition put like Compstat ! 0 in the Alert to ECS step.Also,Is the job setup to Auto rerun?On Control-M for a non-cyclic job to Auto-Rerun,it first has to be in Failed State.Hence regardless of the job being Ended ok