Suppose there is a flow of three jobs like 1A-->1B--1C, now i want the below scenario

In a flow if job 1A runs after 8am, it should not run the script: 1B but go directly to his successor (Pass Condition) 1C

please let me know if there is any other way apart from using scheduling , control resource and conditions

User avatar
philmalmaison
Nouveau
Nouveau
Posts: 1148
Joined: 08 Jun 2007 12:00
Location: Ile de France

Post by philmalmaison » 22 Jun 2011 4:14

Hi,
You can shout to a program after parameter for latesub has been set to 8.AM.
This program can take care about conditions to set
Regards,