Post by Steph » 16 Mar 2011 5:08

I have one job (check of ctmagents ) which stops to be cyclic when it is end not ok.
So I have to restart manually every time it’s failed.
Can I build a option so that when its failed, it will start automatically? (like a script/or option in CtrlM)
Do u have any idea how I can manage it?


As soon as it’s failed, I should normally have an in Alert for investigation.

Do u have any idea how I can manage it?
Many thanks

User avatar
Eight
Nouveau
Nouveau
Posts: 41
Joined: 03 May 2010 12:00

Post by Eight » 21 Mar 2011 8:05

Sounds like you don’t need to stop cyclic so just remove that from the job. If it fails you will still recive an alert/email but the job will continue on its own.

User avatar
TonyP
Nouveau
Nouveau
Posts: 1
Joined: 15 Dec 2010 12:00

Post by TonyP » 23 Mar 2011 10:42

Steph,
it seems you have asked this same question on mutiple posts.
Ejtoedtli's answer on your first post

As he indicated he does not speak french and neither do I used google translate to get the following from his reply to you.

"La commande STOP CYCLIC est votre problème. Vous dites au travail pour arrêter l'exécution comme cyclique. Si vous souhaitez obtenir cet emploi de continuer à fonctionner sur le cycle régulier, peu importe si elle est réussie ou non, alors vous devez supprimer la commande STOP CYCLIQUES de JOB."

Hope this helps