How to depend on a condition ODAT-3

Post by peterrowan » 22 Apr 2010 5:06

I haver a job on Thursday that depends on a job that Runs on Monday.
How do I do In condition ODAT-3 (This is a UNIX server not Z-os). I can create a dummy job to run each day to create a condition on all other days but I risk losing the real dependency on the Monday job

User avatar
Walty
Nouveau
Nouveau
Posts: 473
Joined: 20 Jan 2006 12:00

Post by Walty » 22 Apr 2010 5:37

Hi,

If your job is a regular job you can see this post

If your job is a part of Scheduling Group you can see thispost
Best regards
Walty

User avatar
philmalmaison
Nouveau
Nouveau
Posts: 1148
Joined: 08 Jun 2007 12:00
Location: Ile de France

Post by philmalmaison » 26 Apr 2010 4:52

use the ctmcalc_date utility with shift parameter

regards
philmalmaison

User avatar
philmalmaison
Nouveau
Nouveau
Posts: 1148
Joined: 08 Jun 2007 12:00
Location: Ile de France

Post by philmalmaison » 26 Apr 2010 4:57

sorry for the wrong answer, look at ctmldrns control-M utility
regards
philmalmaison

User avatar
peterrowan
Nouveau
Nouveau
Posts: 22
Joined: 23 Dec 2008 12:00

Post by peterrowan » 26 Apr 2010 5:38

Thanks.