Cyclic job on hold

Tools and several solutions to manage Control-M products
Post Reply
User avatar
craigy66
Nouveau
Nouveau
Posts: 5
Joined: 11 Jun 2007 12:00

Cyclic job on hold

Post by craigy66 » 08 Oct 2009 10:25

We have a cyclic job that loads in every new day and runs every 6 hrs. during the 24 hour period.

If this job is put on hold anytime during the 24 hours; when the hold is taken off, it does not resume it's schedule.

Is this normal for a cyclic job? If not normal, does anyone have an idea what we need to lookat/do?

thanks

User avatar
gglau
Nouveau
Nouveau
Posts: 317
Joined: 13 Jun 2007 12:00

Post by gglau » 09 Oct 2009 2:35

No this is not normal. Click Why on the job after it is freed to see what is is waiting for.

Post Reply