Page 1 of 1

Conditions dependency

Posted: 18 Aug 2015 8:54
by Gopikkd
Take a scenario of two jobs A and B. now establish a dependency b/w them such that job B's In condition should not have Job A's out condition. There should no dependency line shown b/w Jobs A and B. Yet Job B should run only after Job A's completion. How do we achieve this without having to use in and out conditions ?

Re: Conditions dependency

Posted: 30 Oct 2015 8:05
by vamsikumar
Try putting Out condition in Job A in Steps tab. No dependency line between them.. But still A will trigger B