Hi,I know we have a Bypass ->Pre-Submission(Run Now) option to adhocly run a time dependent (or any pre req for that matter) job in EM.However,I have to do this on bunch of jobs(50 or so) at a time and wondering if there is any option to bulk ByPass instead of going to each and every job.

Control-M version is 7

Thanks,
Niras

User avatar
jstarkw
Nouveau
Nouveau
Posts: 58
Joined: 14 Jan 2010 12:00

Re: Bulk By pass time dependent jobs in EM

Post by jstarkw » 30 Jan 2015 10:54

Have you tried highlighting the jobs in the tree view (Left Pane). Highlighting works the same as it does in windows explorer. Then right click on any of the highlighted jobs and select Run now? (Not sure if "Run Now" is in v7 as i use v8.)

nirasm
Nouveau
Nouveau
Posts: 14
Joined: 07 Oct 2014 9:16

Re: Bulk By pass time dependent jobs in EM

Post by nirasm » 05 Feb 2015 7:27

Well no,but I quite think it may work as when I right click on hilighted jobs,the option to 'Pre_Submission(Run Now)' is avaiaible.