Page 1 of 1

Scheduling job

Posted: 07 Nov 2014 12:49
by Croky99
Hello experts,

I need to know how to fill in the scheduling for a new job in Control-M 7.0
This job need to run on the first Monday of the month at 06:00 AM.
I want to use the calendar "Alldays" because I have no rights to make a new calendar, I have no idea if this is possible.
I hope to here something.

Best regards,

Leonard Dronkers

Re: Scheduling job

Posted: 16 Nov 2014 11:09
by Rocket
Hi Leo,

In Week Days section, Rules filed <D1W1> and in Calender select "Alldays"cal. (If ur week start with Monday)

D2W1 if ur week start with Sunday.

Also Submit between field 06:00 AM.

Re: Scheduling job

Posted: 21 Nov 2014 11:30
by Croky99
Hi Rocket,

Thanks for your answer, i'm afraid this is not solving my problem. :cry:
It's has to run on monday morning at 06:00am, so the sunday before it needs to be schedule. In fact it is the first monday of the month, and then 1 day back :D

Greetz Leonard.

Re: Scheduling job

Posted: 24 Nov 2014 2:55
by Rocket
Hi,

When NDP happens? Also time zone for Agent if any!

We normally consider 00:00 as NDP time.

-Sandeep Kolli

Re: Scheduling job

Posted: 24 Nov 2014 7:51
by Croky99
Hi Sandeep,

Our NDP started at 12:00 pm :)

Greetz Leonard.

Re: Scheduling job

Posted: 26 Nov 2014 4:10
by gglau
Schedule it exactly as what you have said.
In fact it is the first monday of the month, and then 1 day back
Set the job to run at 6am on first Monday of each month. Add confirmation calendar to shift one previous day.

Re: Scheduling job

Posted: 02 Dec 2014 11:30
by Croky99
Perfect, that was it :D

Thank guys for helping me.

Grtz Leonard.