Mass HOLD

Post by ANASE » 09 Jun 2010 2:14

Is it possible to define a job in order to hold a list of jobs depending on a filter by NODE ID?
We are using EM 6.2.

User avatar
philmalmaison
Nouveau
Nouveau
Posts: 1148
Joined: 08 Jun 2007 12:00
Location: Ile de France

Post by philmalmaison » 09 Jun 2010 3:44

yes it is use the ctmpsm controlm utility$

regards
philmalmaison

User avatar
Eight
Nouveau
Nouveau
Posts: 41
Joined: 03 May 2010 12:00

Post by Eight » 10 Jun 2010 10:20

Just use Quantitative Resources (Q/R).

* 1st set Q/R in all jobs example: Server-%%NODEID (quantity 1)
* Then define the Q/R in the E/M at Example: 5000
* Then when you want to stop all jobs that require that resource you set Q/R = 0 (no new jobs will start that have the Q/R defined in it).
* To resume set the Q/R back to = 5000