Search found 13 matches
- 01 Jun 2017 3:02
- Forum: Job Definition
- Topic: Job scheduling
- Replies: 2
- Views: 11736
Re: Job scheduling
Hi You can have the last thursday in the month using L1,L2....,L7 and thurdsay selected. The same for tuesday. But you must have an OR operator to explain who will be the last. In that case you don't have other solution to generate a specific calendar. Regards Sorry for the very late answer ;) I di...
- 01 Jun 2017 2:56
- Forum: Job Definition
- Topic: Specific Scheduling Job
- Replies: 1
- Views: 23433
Specific Scheduling Job
Hello, I try to schedule a job who must run on the 25th of the month except if it's a non work day. My new day procedure begin at 12am and the job will be executed at 7am (next day after new day procedure) If the 25 is a sunday, the job must run on friday. If the 25 is an offday (like 05/25/2017), t...
- 19 Aug 2016 2:42
- Forum: Job Definition
- Topic: Job scheduling
- Replies: 2
- Views: 11736
Job scheduling
Hello, I search a specific scheduling for a job. I don't know if it's possible without a dedicate calendar, but we don't want to manage calendar... Job A is scheduled every monday and wednesday and run the day after. Job B must run just after JOB A but only 1 day in the month. The last tuesday or th...
- 03 Nov 2015 5:30
- Forum: Job Definition
- Topic: Schedule job on the last working day
- Replies: 0
- Views: 105060
Schedule job on the last working day
Hello, I need to schedule a ControlM 6.4 job who must execute at 5am (NDP is at 3pm) only on thursday and the last working day of the month. I have a calendar of working day, so I've scheduled it with L2 with calendar WORKINGDAY (Monday to friday). It's ok, but when the last working day is a Monday ...
- 03 May 2011 6:02
- Forum: Control-M Enterprise Manager
- Topic: Gateway stay down after creation
- Replies: 4
- Views: 7668
- 29 Apr 2011 11:19
- Forum: Control-M Enterprise Manager
- Topic: Gateway stay down after creation
- Replies: 4
- Views: 7668
- 28 Apr 2011 4:20
- Forum: Control-M Enterprise Manager
- Topic: Gateway stay down after creation
- Replies: 4
- Views: 7668
Gateway stay down after creation
Hello, I installed a new Control-M/Server in 6.2.01. When i defined the datacenter and create the gateway in admin facility, it stay in status DOWN. I check the ping between EM and Server, telnet => It's OK. Network team has confirmed me that there is no firewall between the 2 machines. How can i te...
- 15 Mar 2011 11:56
- Forum: Control-M Server
- Topic: Migrate ControlM Server v224 to 6.2
- Replies: 0
- Views: 10846
Migrate ControlM Server v224 to 6.2
Hello, I restart a project we had stopped last year. We have a ControlM server v224 running on windows NT4 and DB Sybase. We'll install a new ControlM server v6.2 on windows 2003 and DB SQL 2000. The server is not build for now. I installed the migration toolkit to prepare the migration but when i s...
- 26 Oct 2010 4:29
- Forum: Job Definition
- Topic: Copying scheduling tables/jobs from prod to preprod
- Replies: 2
- Views: 2515
Copying scheduling tables/jobs from prod to preprod
Bonjour, Nous devons migrer notre prod d'un vieux serveur DEC True64 vers un serveur virtuel windows 2003. Pour tester que tout est ok, nous allons tester tout le plan batch sur la recette. L'agent windows sera installé sur le serveur virtuel et il sera connecté au CTM de preprod. J'aimerais connait...
- 19 Oct 2010 11:34
- Forum: ChainView
- Topic: Chainview 3.0
- Replies: 7
- Views: 33154
Hi It's true. so I modified the script without @@runcount not necessary for chainview. You can download the modified version ChainView 3.10 . It should run correctly. Hi, I don't know if I'm alone with this issue but the link doesn't work for me. I can't find the file to download and i'm redirected...
- 22 Sep 2010 4:42
- Forum: Exploitation / Operation
- Topic: Job remain blue
- Replies: 4
- Views: 5734
Sorry, i forgot to give you an answer. I tried this but the ressource was not released. I tried another method: I forced the job in status running and forced to allocate the ressource to the job. And i killed the job. And it was ok. update CMR_AJF set STATE = '4', OSCOMPSTAT=0, STATUS='' where ORDER...
- 26 Jul 2010 4:31
- Forum: Exploitation / Operation
- Topic: Job remain blue
- Replies: 4
- Views: 5734
- 19 Jul 2010 2:20
- Forum: Exploitation / Operation
- Topic: Job remain blue
- Replies: 4
- Views: 5734
Job remain blue
Bonjour, J'ai un probleme avec un job controlm qui reste en waiting control ressource alors que la ressource n'est pas utilisée. J'ai donc essayé de modifier les tables CMR_CTLUSE, CMR_CTL_J et CMR_CTLTAB sans succes. Quelqu'un peut il m'aider sachant que le ControlM est en version 2.2.4 sur un serv...