Search found 3 matches

by PeeWee
24 Feb 2010 12:40
Forum: Exploitation / Operation
Topic: Not possible to run Scheduling Groups multiple times a day
Replies: 9
Views: 8464

Final solution implemented

Hi all, To give a final update to this once more, we couldnt set the time precisely to all the groups at the same time with the @HHMMSS variable. We finally found and succesfully implemented another solution, we made use of the %%APPLIC variable. The %%APPLIC Variable sets the application in which t...
by PeeWee
08 Feb 2010 4:58
Forum: Exploitation / Operation
Topic: Not possible to run Scheduling Groups multiple times a day
Replies: 9
Views: 8464

Hi all, Thanks very much for your reply, it has helped us a lot. Indeed, I managed to set up succesfully the deletions of the conditions. Now, in the Enterprise Manager we still see an overlap in the conditions lines, but indeed Control M is waiting until the condition gets once again an 'Ended-Ok'....
by PeeWee
04 Feb 2010 4:54
Forum: Exploitation / Operation
Topic: Not possible to run Scheduling Groups multiple times a day
Replies: 9
Views: 8464

Not possible to run Scheduling Groups multiple times a day

Hi all, I have a schedule with 12 different Scheduling Groups with dependencies between them. When I want to trigger them again a second time on the same day, the conditions overlap eachother as the schedule has run already once the same day and the name of the condition field is the same. With the ...