Search found 30 matches
- 20 Dec 2011 11:37
- Forum: Control-M Enterprise Manager
- Topic: Schedule Table Access Levels.
- Replies: 4
- Views: 6636
Thank you Fabrizio, I am familiar with the basic security framework, we've currently using Browser/Update/Control access groups. What i want to establish is something between Browse and Update access for the Scheduling Tables. Browse is basically read-only and Update is very permissive. For example ...
- 19 Dec 2011 11:03
- Forum: Control-M Enterprise Manager
- Topic: Schedule Table Access Levels.
- Replies: 4
- Views: 6636
Schedule Table Access Levels.
Hi, I need to create some specific permissions. That is to allow users to browse the schedule tables and widely admin the jobs in the AJF including Order in Jobs. BUT we must revoke the ability to Upload new job definitions into the tables or add new scheduling tables. Basically separate the support...
- 07 Nov 2011 10:26
- Forum: Job Definition
- Topic: Use of Variables in paths including \
- Replies: 5
- Views: 4292
- 05 Nov 2011 10:08
- Forum: Job Definition
- Topic: Use of Variables in paths including \
- Replies: 5
- Views: 4292
- 04 Nov 2011 5:26
- Forum: Job Definition
- Topic: Use of Variables in paths including \
- Replies: 5
- Views: 4292
Use of Variables in paths including \
Hi Folks. CTM 6.4.0.1, all the lastest service packs on Wintel. I'm tearing my hair out here, please help. :oops: I am trying to specify an output folder for a report using variables to distribute the reports into sub folders... so the path looks like this: \\server01\E$\reports\2011\11\... I have u...
- 04 Feb 2011 1:35
- Forum: Control-M Control Module
- Topic: Control-M Server Port 2370
- Replies: 3
- Views: 5117
Control-M Server Port 2370
Hi Folks, I have some unusual port behaviour on a Control-M Server, wondering what might cause it. From the /EM server I use TCPView to check that ports 2369, 2370 and 2371 are open and available on a remote Control-M Server. The port are open and operational and everything appears fine. Local Addre...
- 09 Dec 2010 2:08
- Forum: Reporting
- Topic: Audit Reports.
- Replies: 1
- Views: 3586
Audit Reports.
Hi Everyone. I need to produce a report which captures all manual activities which result in Jobs being added to the AJF. Critically I need to ensure the total number of Jobs in the schedule is full accountable. The Report Facility - Audit Report + some extra fields does give a list off many 'operat...
- 30 Sep 2010 12:43
- Forum: Control-M Forecast
- Topic: Projecting future job usage.
- Replies: 1
- Views: 7584
Projecting future job usage.
Hi Guys, Quick question about the features in /Forecast. At this time i only really need to calculate the number of jobs on a given date in the future. Is Forecast overkill? It certainly appears to have a lot more power then that. It was the first application which came to mind but if this is possib...
- 24 Sep 2010 12:22
- Forum: Monitoring
- Topic: GUI shows Waiting status even after execution
- Replies: 1
- Views: 3990
GUI shows Waiting status even after execution
Hi Folks. Wintel / CTM 6.4.01.200 on all components. I had a couple of weird problems last night. :roll: Two jobs that have successfully executed on an /Agent don't update their status in the /EM GUI. Dependant jobs continue to process normally as if there is no problem. If I 'hold' the 'stuck' job ...
- 16 Sep 2010 12:10
- Forum: Control-M Server
- Topic: Reinstalling / Replacing a Server
- Replies: 2
- Views: 2856
- 15 Sep 2010 1:25
- Forum: Job Definition
- Topic: MaxWait - Simple Question.
- Replies: 2
- Views: 2754
- 15 Sep 2010 12:18
- Forum: Control-M Server
- Topic: Reinstalling / Replacing a Server
- Replies: 2
- Views: 2856
Reinstalling / Replacing a Server
I folks. I need to reinstall one of my Control-M/Servers and would appropriate any advice or previous experience of this activity. I want retain the same name, IP and general configuration but during the install i'll be able to specify different remote MSSQL database location and service accounts et...
- 15 Sep 2010 11:20
- Forum: Job Definition
- Topic: MaxWait - Simple Question.
- Replies: 2
- Views: 2754
MaxWait - Simple Question.
Hi Folks. Will the MaxWait variable keep a job in the AJF if the job is End-OK? For example: A Job has a MaxWait = 10. On Day3 the job executes and End-OK. After the New Day process on Day4 will the job be retained? I couldn't see anything specific in the manual, it suggested the MaxWait would only ...
- 15 Apr 2010 1:07
- Forum: Reporting
- Topic: Report Field for 'Last RunTime'
- Replies: 2
- Views: 2391
Report Field for 'Last RunTime'
Hi Guys, I checked this recently but I can't believe 6.4.01.200 is not able to provide this value via Report Facility so thought I should check again. Each morning I need a report to list how long each job took to run. Simple I would think. I need the Actual Runtime . The closest I can get it the Av...
- 04 Mar 2010 11:43
- Forum: Reporting
- Topic: Report Facility - Error with Time Frames.
- Replies: 0
- Views: 11895
Report Facility - Error with Time Frames.
I'm getting a weird issue when creating a 'Time Frame' in the report wizard. CTRLM ver: 6.4.1.200 :D I'm using a default Workload Distribution Report . It saves and runs fine when select 'last 100 days ' for example. :? If i select 2 dates using the "from date" "to date" I can't save the report temp...