STATISTICAL informations are not updated in Control-M EM

Hi All, Statistical informations of all the jobs in datacenter is not updating in Control-M EM. But the jobs are running fine, sysout and logs are fine. we are able to see the sysout and logs except statistical info. What could be the reason for only statistical information is not updating. We ran t...
by Senthilkumar
19 Dec 2012 2:54
Forum: Job Definition
Topic: Need help : ON & CODE issue.
Replies: 4
Views: 4952

Hi, The Requirement is if the job failure with other error they need the mail stating the "job failed with Error. Hence STOPPING the Batch chain" If the job is failed with 180 then it should continue the batch send an email stating that " FAILED with ERROR 180. Hence Continuing the BATCH". Thanks, S...
by Senthilkumar
19 Dec 2012 9:06
Forum: Job Definition
Topic: Need help : ON & CODE issue.
Replies: 4
Views: 4952

Need help : ON & CODE issue.

Hi All, Need help on the below We have batch of 50 jobs and in that middle of the job (for ex : 28), which it returns the code as 180 then it should continue the batch and mail sent to the customer, other than 180 and non zero then it should stop the batch and mail need to send to the customer that ...
by Senthilkumar
12 Sep 2012 1:32
Forum: Job Definition
Topic: smart table not changing the colour after all jobs ended ok.
Replies: 0
Views: 20717

smart table not changing the colour after all jobs ended ok.

Hi All, We are using the control-m version 7.0. created some jobs under smart tables, In Control-M EM all the jobs under the smart tables are completed successfully. but still the smart table as showing as yellow colour it is not changing the colour. Under the smart table, we have multiple groups of...
by Senthilkumar
10 Sep 2012 1:56
Forum: Monitoring
Topic: Jobs are not completing after it ended ok in the log
Replies: 3
Views: 7370

Jobs are not completing after it ended ok in the log

Hi All, We have some jobs created in SMART tables. Today the job completed in the agent level and we are getting the information in the log also, but still the job is showing as yellow colour and it is not passing the condition to the dependent jobs. what will be the reason for status not updating i...
by Senthilkumar
29 Aug 2012 3:37
Forum: Control-M Enterprise Manager
Topic: Alerts for "STATUS OF AGENT PLATFORM xxx CHANGED TO AVA
Replies: 1
Views: 3287

Alerts for "STATUS OF AGENT PLATFORM xxx CHANGED TO AVA

Hi,

We are receiving the alerts for the agent available status. How to disable the alert for the "STATUS OF AGENT PLATFORM xxxxxxx CHANGED TO AVAILABLE" in GAS.

We are using Control-M 7.0.00.300



Thanks in advance.

Senthil.
by Senthilkumar
22 Aug 2012 6:17
Forum: Control-M Server
Topic: Patch update in Control-M Server (windows)
Replies: 0
Views: 21804

Patch update in Control-M Server (windows)

Hello All, We have the control-m set up in Windows. Want to do windows patching on both control-m server and database. Control-M A (primary/production) has a failover server Control-M B Control-M A's DB has mirror established with Control-M B's DB. Both control-m servers and EM hosted in Windows and...
by Senthilkumar
12 Mar 2010 1:34
Forum: Job Definition
Topic: Execution time clarification
Replies: 7
Views: 3559

Execution time clarification

If you want to run a job not before 22:00 and run after the newday (depends on the resource Availablity). In the Time '2200' and until '>'. so It wont start before 2200 and it will run once the quantitative resource are available. some times during the maintenance time, we used to do the same (that...
by Senthilkumar
30 Jun 2009 3:47
Forum: Job Definition
Topic: Condition Tab of the Job Editing Panel
Replies: 4
Views: 6459

DATES ON CONDITIONS

Hi Friends,

Thanks for the Information.

~Senthil.
by Senthilkumar
29 Jun 2009 11:31
Forum: Job Definition
Topic: Condition Tab of the Job Editing Panel
Replies: 4
Views: 6459

Condition Tab of the Job Editing Panel

Hi,

Greetings :).

In control-m, the Job Editing panel/Condition tab has the following values

$$$$ ,
**** ,
STAT,
ODAT,
NEXT,
PREV .

can anyone expalin me what it means?

Thanks in advance.

~Senthil.
by Senthilkumar
14 May 2009 10:05
Forum: Reporting
Topic: Send an e-mail when a job is finished OK
Replies: 4
Views: 3523

Hi, In Control-M Enterprise Manager, u can try in the Job Editing Form / Post Proc panel 'When' is equal to 'Ok', then type the mail id in the 'To' option. or otherwise if you want the sysout of the job u can use the PARM Perameter in the Job Editing Form/<%> Set panel. Please correct me when i am w...
by Senthilkumar
14 May 2009 9:45
Forum: General News
Topic: Reg the Control-M Admin Certification
Replies: 1
Views: 10010

Reg the Control-M Admin Certification

Hi All,

Greetings :)

I am using Control-M 6.2.01.300 since 2007. i want to do the certification in Control-M Adminstrator .

How can i do that? is there any critiria for that doing the Administrator?

Could anyone please help me ?

Thanks in advance.

~ Senthil.