Search found 5 matches

by Fredmon
04 Nov 2011 7:55
Forum: Control-M Forecast
Topic: Forecast - Control M/Desktop 6.4.01
Replies: 1
Views: 9341

Forecast - Control M/Desktop 6.4.01

When adding user daily jobs to the Forcasting User Daily Defination I was wondewring if there a max of user daily jobs that can be defind. Right now I have about 65 tables defined but couldn't add any new ones. I would receive this message 'There are no more user dailys to add' but I know for a fact...
by Fredmon
11 Mar 2011 9:13
Forum: Control-M Enterprise Manager
Topic: Cyclic Dependent job
Replies: 8
Views: 7208

Niras,
have you tried setting the maxwait 0 / blank. give that a try and see if it works. Good luck.
by Fredmon
10 Mar 2011 8:15
Forum: Control-M Enterprise Manager
Topic: Cyclic Dependent job
Replies: 8
Views: 7208

Niras, you have a couple of options. 1) You can set jobA up using the forcejob command so that it forces in jobB when jobA completes successfully. 2) I think you kind of mentioned this approach but you can set up both jobs as cyclic jobs with the two times specified in each job. Then have jobA as a ...
by Fredmon
18 Oct 2010 10:45
Forum: Exploitation / Operation
Topic: time between job
Replies: 5
Views: 4053

how would you set the sleeper command up to work in SAP jobs. I use it with UNIX jobs, command sleep 3600 (1 hr). Any ideas
by Fredmon
18 Apr 2008 7:27
Forum: Job Definition
Topic: Scheduling a job, previous business day, not in calendar
Replies: 4
Views: 4149

Well we have run into a similar problem using in-statement conditions with dates. We have jobs schedule Monday - Firday that require the previous days run to be completed successfully. So we have created 'odate" jobs using autoedits to calculate the date and send completion In-statements for the nex...